Engineer
Handbook

Field procedures, commissioning checklists and handover documentation for every discipline.

Quick Access — Most Used Procedures
Fire Walk Test
BS 5839-1 procedure
Intruder Walk Test
All zones verified
Battery Check
Load test procedure
Handover Checklist
Completion documentation
Cable Resistance
Loop resistance reference
Fault Finding
Systematic diagnosis
Access Control
Annual Service Procedure — Access Control
Door controllers · Readers · Electric locks · Software audit · Cardholder review
Annual Service Checklist
Review event log. Check for access denied events, door forced alarms, door held-open alarms, and any unusual access patterns.
Test each door: present valid credential — verify door unlocks and re-locks after hold-open time. Test REX button. Test door contact.
Inspect all electric/magnetic locks. Check mounting security, armature plate alignment, and holding force. Lubricate door hinges and closers as required.
Inspect all readers for physical damage, loose mounting, or tampering.
Test fail-safe operation: disconnect power to lock — verify door opens freely (fail-safe) or remains locked (fail-secure) as per design.
Test fire alarm integration: trigger fire alarm input — verify all fire escape doors release to fail-safe position.
Carry out cardholder audit: review active credentials. Remove credentials for leavers, temporary staff, and contractors. Advise client to report leavers promptly.
Review access levels and time zones. Confirm they still reflect current business requirements.
Check software and firmware versions. Apply updates if available and appropriate.
Verify backup of system configuration is current.
Issue service report. Record all test results, defects found, and recommendations.
CCTV
Annual Service Procedure — CCTV System
Camera inspection · Recording verification · Storage health · GDPR review
Annual Service Checklist
Inspect all cameras: check physical condition, mounting security, lens cleanliness, and IR illuminator operation (at night or in a dark environment).
Verify live image quality for all cameras. Check for focus drift, condensation, spider webs, or vegetation obscuring the field of view.
Verify all cameras are recording. Check NVR/VMS for any cameras showing offline, no signal, or recording errors.
Test playback: retrieve and play back footage from each camera. Verify footage is clear, timestamped correctly, and covers the required retention period.
Check storage health: verify HDD/SSD SMART status on NVR. Check available storage and confirm retention period is being met.
Verify NVR/VMS time and date are correct and synchronised (NTP).
Check network connectivity: verify all cameras are reachable on the network. Check for IP conflicts.
Review motion detection settings. Confirm detection zones are still appropriate and sensitivity is not causing excessive false triggers.
Check firmware versions on cameras and NVR. Apply security updates if available.
GDPR review: confirm CCTV signage is still in place and legible. Confirm retention period policy is being followed. Confirm ICO registration is current.
Issue service report. Record all findings, any cameras replaced or adjusted, and any recommendations.
Fire Alarm
Annual Service Procedure — Fire Alarm
BS 5839-1 · Quarterly, six-monthly and annual inspection requirements
BS 5839-1 Clause 45: Fire alarm systems must be inspected and tested at regular intervals by a competent person. The minimum frequency is every six months, with a full test annually. Quarterly testing is recommended for larger or higher-risk systems.
Every Visit (Minimum Six-Monthly)
Review the fire alarm log book. Note any faults, false alarms, or activations since the last visit.
Inspect the panel for any current faults or warnings. Clear any outstanding faults and investigate root cause.
Test a representative sample of detectors and call points (minimum one-third of all devices per visit, rotating so all devices are tested within 12 months).
Test all sounders and VADs. Verify correct operation and adequate sound levels.
Test all cause and effect outputs (door releases, AHU shutdown, lift recall, suppression system interface).
Test ARC signalling. Confirm ARC receives test signal correctly.
Inspect all visible cabling for damage, deterioration, or unauthorised modifications.
Inspect all detectors for contamination, damage, or obstruction. Clean or replace as required.
Check battery condition. Measure voltage under load. Replace if below manufacturer's minimum threshold.
Verify panel time and date are correct.
Annual (Full Test)
Test 100% of all detectors and call points.
Full battery load test: disconnect mains and verify standby duration meets BS 5839-1 requirements (typically 24 hrs standby + 30 min alarm for L-grade systems).
Inspect all junction boxes, terminal connections, and cable entries for security and condition.
Review zone plan and as-installed drawings. Update if any changes have been made to the building or system.
Issue a service report and update the log book. Note any recommendations or defects requiring remedial work.
Intruder Alarm
Annual Service Procedure — Intruder Alarm
EN 50131 · PD 6662 · NSI / SSAIB maintenance requirements
NSI/SSAIB requirement: Intruder alarm systems installed to NSI Gold or SSAIB standards require a minimum of one annual service visit. Grade 3 and above systems may require more frequent visits. Always refer to the maintenance contract and certification body requirements.
Annual Service Checklist
Review system log / event history. Note any false alarms, faults, or activations since last visit. Investigate any patterns.
Inspect panel: check for faults, tamper alerts, low battery warnings. Clear and investigate all outstanding events.
Test all detection zones: open each door contact, walk each PIR, trigger each shock sensor. Verify correct zone identification on panel.
Test all tamper circuits: open each device housing. Verify tamper alarm is generated on panel.
Test all PA (personal attack) buttons.
Test bell box: trigger alarm and verify external sounder and strobe activate. Confirm bell cut-off timer operates correctly.
Test ARC signalling: arm system, trigger alarm, and confirm ARC receives correct signal. Test restore signal.
Battery load test: disconnect mains. Verify battery voltage remains above minimum under load. Check charger output voltage (typically 13.8V for 12V SLA).
Inspect all visible cabling for damage or unauthorised modifications.
Verify entry/exit delays are appropriate and have not been changed without authorisation.
Verify user codes are known to the client. Advise client to change codes if there has been a change of staff.
Issue service report. Record all test results, any defects found, and any remedial work carried out or recommended.
General Reference
ARC Signalling Setup & Testing
Dual-path signalling · Contact ID / SIA protocol · Account numbers · Test procedures
Signalling Protocols
ProtocolDescriptionTypical Use
Contact IDIndustry-standard DTMF-based protocol. 4-digit account number + 3-digit event code + zone number.Fire and intruder alarms via PSTN/VoIP
SIA DC-09IP-based protocol. Encrypted, acknowledged, supports extended event codes.IP signalling (broadband/4G)
SIA Level 3Enhanced SIA with encryption and acknowledgement.High-security IP signalling
Fast FormatLegacy Scancom/Ademco protocol.Older PSTN installations
Dual-Path Signalling (BS 8243 / EN 50136)
Primary path: Broadband IP (SIA DC-09). Fastest and most reliable for modern installations.
Backup path: 4G/GPRS cellular. Activates automatically if primary path fails. Required for Grade 3 and above.
Dual-path providers: Dualcom (CSL), Redcare (BT), Emizon, Pyronix CloudLink, Texecom Premier Elite IP.
Programming Checklist
01
Obtain account number from ARC. Programme into panel communicator.
02
Programme ARC telephone number or IP address/port into communicator.
03
Select correct protocol (Contact ID for PSTN/VoIP, SIA DC-09 for IP).
04
Map all event codes: alarm, restore, tamper, fault, arm, disarm, test call.
05
Programme periodic test call (typically every 24 hours). Confirm ARC is expecting it.
06
Test all signals: trigger alarm, tamper, fault. Confirm ARC receives each event with correct account number and event code.
07
Test backup path: disconnect primary path. Trigger alarm. Confirm ARC receives signal via backup path.
General
Battery Standby Load Test
Fire and intruder alarm systems · BS 5839-1 requires 24h standby + 30min alarm · BS EN 50131 requires 12h or 24h standby
Battery Requirements
System TypeStandby DurationAlarm DurationStandard
Fire Alarm (non-domestic)24 hours30 minutes full alarmBS 5839-1
Fire Alarm (dwelling, Grade A)24 hours4 minutes full alarmBS 5839-6
Intruder Alarm (Grade 2)12 hours30 minutesPD 6662 / BS EN 50131
Intruder Alarm (Grade 3)24 hours30 minutesPD 6662 / BS EN 50131
Load Test Procedure
01
Disconnect mains supply to the panel. The system should switch to battery backup.
02
Measure battery voltage under load (system running on battery). Voltage should remain above the minimum operating voltage for the required standby period.
03
After the standby period, trigger the alarm output. Verify the system can sustain full alarm output for the required alarm duration.
04
Reconnect mains supply. Verify the system returns to normal and begins recharging the battery.
Battery Replacement
01
Notify the ARC before disconnecting the panel.
02
Isolate mains supply. Note: some panels retain memory from battery — do not disconnect battery and mains simultaneously.
03
Replace battery with same capacity and voltage. Use sealed lead-acid (SLA) or VRLA type as specified by manufacturer.
04
Reconnect mains. Allow battery to charge for at least 24 hours before carrying out a load test.
Battery life: SLA batteries in fire and intruder systems should be replaced every 3–4 years as part of routine maintenance, regardless of apparent condition. A battery that passes a voltage test may still fail under load.
General Reference
Cable Resistance Reference Tables
Loop resistance · CSA vs resistance · EOL resistor values · Common panel maximums
Copper Cable Resistance (per conductor)
CSAResistance (Ω/km)Max Loop (100Ω limit)Max Loop (500Ω limit)
0.5mm²36.0 Ω/km1,389 m (one way)6,944 m (one way)
1.0mm²18.1 Ω/km2,762 m (one way)13,812 m (one way)
1.5mm²12.1 Ω/km4,132 m (one way)20,661 m (one way)
2.5mm²7.41 Ω/km6,748 m (one way)33,738 m (one way)
EOL Resistor Values by Panel Manufacturer
PanelEOL Resistor ValueNotes
Galaxy Dimension1kΩ (1,000Ω)Standard zones. Double pole EOL for Grade 3.
Galaxy Flex1kΩ (1,000Ω)Same as Dimension.
Galaxy MK71kΩ (1,000Ω)Legacy panel — same value.
Texecom Premier Elite1kΩ (1,000Ω)Default. Can be changed in programming.
Pyronix Enforcer2.2kΩ (2,200Ω)Standard. Check programming for custom values.
Eaton i-on4.7kΩ (4,700Ω)Standard value.
DSC Neo5.6kΩ (5,600Ω)Default. Configurable in programming.
Risco LightSYS 22.2kΩ (2,200Ω)Standard value.
Bosch Solution 30001kΩ (1,000Ω)Standard value.
Fire Alarm Cable Specifications
Cable TypeStandardApplicationFire Resistance
FP200 GoldBS 7629-1Fire alarm wiring — standard30 min (E30) or 60 min (E60)
MICC (Pyrotenax)BS EN 60702High-risk environments, sprinkler systems120 min (E120)
Standard PVCBS 6004NOT suitable for fire alarm wiringNone
LSF/LSZHBS 7211Intruder alarm, access control, CCTVNone (low smoke/zero halogen)
Fire Alarm
Cause and Effect Matrix
Programming outputs · Door releases · AHU shutdown · Suppression interfaces · Testing
What is a Cause and Effect Matrix?
A document (and panel programming) that defines exactly which outputs activate in response to which inputs. Agreed between the designer, client, and fire risk assessor before commissioning.
Must be tested in full during commissioning (every cause triggered, every effect verified). Results documented on the commissioning certificate.
Common Causes (Inputs)
CauseTypeNotes
Zone 1 alarm (1 detector)Single detector alarmMay trigger pre-alarm only (coincidence detection).
Zone 1 alarm (2 detectors)Coincidence alarmTriggers full evacuation outputs.
Manual call pointImmediate alarmAlways triggers full evacuation — no coincidence required.
Suppression system inputAbort / dischargeMay trigger pre-discharge warning, then discharge.
Fault conditionFault outputMay trigger BMS/BEMS fault signal.
Common Effects (Outputs)
EffectOutput TypeWiring
All soundersSounder circuit(s)Normally-open relay or sounder bus.
Door release (hold-open)Normally-energised relayPower removed on alarm — door closes.
AHU shutdownNormally-energised relayPower removed on alarm — AHU stops.
Lift recallNormally-open relayRelay closes on alarm — lift returns to ground.
Suppression releaseNormally-open relayRelay closes on alarm — activates suppression.
ARC signallingIP/PSTN communicatorTransmits alarm signal to monitoring centre.
Smoke controlNormally-open relayOpens AOVs / activates smoke extract fans.
Access control releaseNormally-energised relayPower removed on alarm — all doors fail-safe open.
Testing Procedure
1
Obtain the agreed cause and effect matrix document before testing.
2
Trigger each cause in turn (use panel test mode to avoid full evacuation during testing).
3
Verify every expected effect activates. Tick each cell on the matrix as confirmed.
4
Verify effects that should NOT activate do not activate (negative testing).
5
Document any discrepancies and correct before handover. Re-test corrected items.
6
Attach completed matrix to the commissioning certificate and O&M manual.
CCTV
CCTV Storage Calculation
Bitrate · Retention period · HDD sizing · H.264 vs H.265 · Worked examples
Storage Formula
Storage (GB) = (Bitrate Mbps ÷ 8) × 3600 × Hours/day × Days × Cameras ÷ 1000
Add 10–15% overhead for filesystem and NVR metadata.
Typical Bitrates by Resolution
ResolutionH.264 BitrateH.265 BitrateNotes
2MP (1080p)2–4 Mbps1–2 MbpsStandard commercial camera.
4MP (1440p)4–6 Mbps2–3 MbpsGood detail for medium areas.
8MP (4K)8–16 Mbps4–8 MbpsHigh detail — large storage requirement.
PTZ (2MP)4–8 Mbps2–4 MbpsHigher bitrate due to motion.
Worked Example
16 cameras × 4MP H.265 × 3 Mbps bitrate × 24 hrs × 31 days retention.
Storage = (3 ÷ 8) × 3600 × 24 × 31 × 16 ÷ 1000 = 6,220 GB ≈ 6.2 TB
With 15% overhead: 6.2 × 1.15 = 7.1 TB minimum HDD capacity. Specify 2× 4TB or 1× 8TB HDD.
UK GDPR Retention Requirements
Premises TypeRecommended RetentionNotes
General commercial31 daysICO CCTV Code of Practice recommendation.
Retail (high footfall)31 daysAllows time for incidents to be reported.
Car park31 daysMinimum. Some operators use 90 days.
Incident footageUntil resolvedMust be preserved — do not allow overwrite.
Subject Access RequestUntil SAR resolvedPreserve relevant footage immediately on receipt of SAR.
HDD Selection
Use surveillance-grade HDDs (e.g. Seagate SkyHawk, WD Purple) — rated for 24/7 operation and high write cycles. Standard desktop HDDs will fail prematurely in NVR applications.
For critical installations, use RAID 1 (mirroring) or RAID 5 for redundancy. RAID is not a backup — implement a separate backup strategy for critical footage.
General Reference
Commissioning Certificates & Documentation
What to produce · What to include · Log books · O&M manuals · Retention
Required Documentation by System
SystemRequired DocumentsStandard
Fire alarmCommissioning certificate, as-installed drawings, cause & effect matrix, log book, O&M manual, FD&A certificate (if applicable)BS 5839-1:2025 Clause 44
Intruder alarmCommissioning certificate, system specification, zone schedule, user manual, log bookPD 6662, EN 50131
Access controlCommissioning certificate, door schedule, credential list (encrypted), user manual, network diagramBS EN 60839-11-1
CCTVCommissioning certificate, camera schedule, network diagram, privacy notice, GDPR documentation, user manualICO CCTV Code of Practice
Fire Alarm Log Book Requirements
Must be kept at the premises. Must be updated after every visit: commissioning, service, fault attendance, false alarm, and any system modification.
Each entry must include: date, engineer name, company, work carried out, any defects found, and any outstanding work.
The Responsible Person must countersign each entry. The log book is a legal document and may be inspected by the Fire and Rescue Service.
Commissioning Certificate — Minimum Content
Site name and address. System type and category. Panel make, model, and serial number. Date of commissioning. Engineer name and certification number.
List of all devices tested with pass/fail result. Cause and effect test results. Battery test results. Any outstanding defects or deviations from the design specification.
Declaration that the system has been installed and commissioned in accordance with the relevant standard.
Document Retention
Fire alarm records: retain for the life of the building. Log books must not be disposed of.
CCTV commissioning records: retain for the life of the system. GDPR documentation: retain for the life of the system plus 6 years.

No results found matching your search.

Access Control
Commissioning Checklist — Access Control
Door controllers · Readers · Electric locks · Network setup · Cardholder enrolment
First Fix
01
Install cable containment. Run Cat5e/Cat6 for IP-based systems. Run 4-core screened cable for Wiegand readers. Run 2-core for door contacts and REX buttons.
02
Install door controller back-boxes, reader back-boxes, REX button back-boxes, and door contact frames.
03
Install electric lock or magnetic lock. Ensure door frame is correctly prepared for lock type. Verify door closer is fitted and adjusted.
Second Fix
04
Fit all readers, REX buttons, and door contacts. Connect to door controller per wiring diagram.
05
Connect electric lock to controller. Verify fail-safe or fail-secure operation matches design intent.
Fail-safe (fail-open): lock releases on power loss — required for fire escape routes. Fail-secure (fail-locked): lock remains locked on power loss — used for security-critical doors.
06
Connect door controller to network switch. Assign static IP or configure DHCP reservation. Verify controller is reachable from server.
07
Power up system. Verify all door controllers appear online in management software.
08
Configure door schedules, access levels, and time zones in management software.
09
Enrol administrator credentials. Change all default passwords on controllers and software.
10
Test each door: present valid credential — verify door unlocks and re-locks after the configured hold-open time. Test REX button — verify door unlocks. Test door contact — verify open/close status is logged.
11
Test access denied: present invalid credential — verify door remains locked and event is logged.
12
Test fire alarm integration (if applicable): trigger fire alarm input — verify all doors release to fail-safe position.
13
Complete commissioning documentation. Provide client with administrator login credentials and user training.
CCTV
Commissioning Checklist — CCTV System
IP cameras · NVR/DVR setup · Network configuration · GDPR compliance
First Fix
01
Install cable containment. Run Cat5e/Cat6 for IP cameras (PoE). Run RG59 or RG6 coax for analogue cameras. Label all cables at both ends.
02
Install camera back-boxes and mounting brackets. Ensure mounting surface is structurally sound. Position cameras to achieve required coverage per CCTV design.
03
Install NVR/DVR in secure location (locked cabinet recommended). Install PoE switch if required.
Second Fix
04
Fit all cameras. Connect to PoE switch or NVR PoE ports. Verify each camera powers up.
05
Assign static IP addresses to all cameras. Use a dedicated VLAN for CCTV traffic where possible.
06
Add all cameras to NVR/VMS. Verify live view is available for all cameras.
07
Adjust camera angles and focus. Set zoom level. Verify image quality meets design specification (e.g. facial recognition requires minimum 250px/m at point of interest).
08
Configure recording schedules: continuous, motion-triggered, or scheduled. Set retention period (minimum 31 days recommended for most sites; 90 days for high-security).
09
Configure motion detection zones and sensitivity. Test motion detection triggers recording correctly.
10
Change all default passwords on cameras, NVR, and VMS software. Enable HTTPS/SSL where available.
11
Apply privacy masking to any areas that should not be recorded (neighbouring properties, public areas outside the site boundary).
12
Verify storage capacity: confirm total storage meets the required retention period at the configured recording quality.
13
Test remote access (if applicable). Verify VPN or secure remote viewing is functional.
14
Complete GDPR documentation: CCTV policy, signage audit, Data Protection Impact Assessment (DPIA) if required, ICO registration check.
15
Complete commissioning documentation and client handover. Train client on playback, export, and system management.
UK GDPR: CCTV is personal data. The operator must have a lawful basis for processing, display appropriate signage, and respond to Subject Access Requests within 30 days. Register with the ICO if processing personal data.
Fire Alarm
Commissioning Checklist — Fire Alarm
First-fix through to handover · BS 5839-1 compliant
First Fix
01
Install all cable containment (conduit, trunking, cable tray). Ensure fire-rated containment where required by design.
FP200 Gold or equivalent enhanced fire performance cable required for all fire alarm wiring.
02
Pull all fire alarm cables. Label each cable at both ends with zone number and device type.
03
Install all detector bases, call point back-boxes, sounder back-boxes, and VAD back-boxes. Do not fit devices at this stage.
04
Install panel back-box and cable entry. Do not connect cables to panel at this stage.
Second Fix
05
Connect all loop cables to panel. Verify loop continuity with multimeter before powering up.
Measure resistance of each loop — should be consistent with cable CSA and length.
06
Address all devices (if addressable system). Use manufacturer's addressing tool or DIP switches. Record addresses on as-installed drawings.
07
Fit all detectors, call points, sounders, and VADs.
08
Power up panel. Check all devices are recognised and showing normal status.
09
Programme panel: zone labels, cause and effect, time/date, ARC signalling, remote access.
10
Carry out full walk test (see Walk Test procedure).
11
Test all outputs: sounders, VADs, door releases, ARC signalling, remote monitoring.
12
Carry out battery load test (see Battery Check procedure).
13
Complete all commissioning documentation and handover to client (see Handover Checklist).
Intruder Alarm
Commissioning Checklist — Intruder Alarm
First-fix through to handover · EN 50131 / PD 6662 compliant
First Fix
01
Install all cable containment. Use LSZH cable throughout. Segregate intruder cabling from mains wiring by a minimum of 50mm or use a metallic barrier.
02
Pull all detection zone cables, bell circuit cables, and keypad cables. Label at both ends with zone number and device type.
03
Install all PIR back-boxes, door contact frames, keypad back-boxes, and bell box back-boxes. Do not fit devices at this stage.
04
Install panel back-box. Ensure it is in a secure, accessible location — typically a cupboard or plant room. Panel must be tamper-protected.
Second Fix
05
Fit all PIR detectors, door contacts, and keypads. Fit bell box. Check all tamper switches are engaged.
06
Connect all zone cables to panel. Install EOL resistors at the end of each zone (value per manufacturer specification).
07
Connect bell circuit. Verify bell box tamper and strobe wiring.
08
Power up panel. Check all zones show normal (closed) status. Check tamper circuit shows normal.
09
Programme panel: zone labels, zone types (entry/exit, instant, 24hr), entry/exit delays, alarm confirmation timers, user codes, engineer code, ARC signalling path.
10
Carry out full walk test (see Walk Test — Intruder Alarm procedure).
11
Test ARC signalling: arm and trigger alarm. Confirm ARC receives correct signal with correct account number and zone description.
12
Test all outputs: internal sounder, external bell box, strobe, ARC signalling.
13
Carry out battery load test. Verify standby duration meets EN 50131 Grade requirement (Grade 2: 12 hrs standby + 4 min alarm; Grade 3: 12 hrs + 4 min).
14
Set engineer code to a unique value. Do not leave factory default. Record in site documentation.
15
Complete commissioning documentation and handover to client (see Handover Checklist).
Grade compliance: The installed grade must match the system design. Grade 2 is standard for most commercial premises. Grade 3 requires additional tamper protection, dual-path signalling, and enhanced power supply.
Fire Alarm
Detector Cleaning & Replacement
Dirty detector faults · Cleaning procedure · Replacement intervals · Aspirating systems
Dirty Detector Fault
An analogue addressable panel generates a "dirty detector" or "service required" fault when a detector's analogue value has drifted beyond the panel's compensation range, indicating contamination that cannot be automatically corrected.
Do not ignore dirty detector faults — a contaminated detector may be insensitive to real smoke, or may generate false alarms. Attend within the maintenance contract SLA.
Cleaning Procedure (Optical Smoke Detector)
1
Isolate the zone at the panel (or use panel test mode) to prevent false alarms during cleaning.
2
Remove the detector from its base. Note the address before removal.
3
Use a detector cleaning kit (compressed air or specialist vacuum with HEPA filter) to remove dust from the detection chamber. Do not use water or solvents.
4
Refit the detector. Check the panel — the dirty detector fault should clear. If it does not clear, replace the detector.
5
Re-enable the zone and confirm normal operation. Log the cleaning in the system log book.
Replacement Intervals
Detector TypeRecommended ReplacementNotes
Optical smoke detector10 years from manufactureBS 5839-1 recommendation. Replace earlier if repeated dirty faults.
Heat detector10 years from manufactureCheck date code on detector.
Multi-sensor detector10 years from manufactureAs above.
Aspirating detector (VESDA)Per manufacturer guidanceLaser source typically 10 years. Filter replacement annually.
Manual call pointReplace if damaged or after operationTest glass/element must be replaced after activation.
Fire Alarm
Detector Spacing — Smoke & Heat (BS 5839-1)
Flat ceiling spacing rules · Sloped ceiling adjustment · Wall-mounted detectors · Zone coverage
Flat Ceiling — Standard Spacing (BS 5839-1 Table 4)
Detector TypeMax Distance Between DetectorsMax Distance to WallMax Floor Area per Detector
Smoke (optical / ionisation)7.5 m3.75 m80 m²
Heat (A1R, A1S, BS)5.3 m2.65 m30 m²
Multi-sensor (smoke + heat)7.5 m3.75 m80 m²
CO detector7.5 m3.75 m80 m²
Sloped Ceiling Adjustment
For ceilings sloped at more than 20°, place the first row of detectors within 600mm of the apex (ridge).
Subsequent rows are spaced at the standard horizontal distance measured along the slope.
For very steep roofs (>45°), the apex row may be the only row required if the floor area per detector is not exceeded.
Ceiling Height Considerations
Ceiling HeightDetector TypeNotes
Up to 6 mSmoke or heatStandard spacing applies.
6 m – 12 mSmoke preferredHeat detectors may not respond adequately due to thermal stratification. Reduce spacing or use beam detectors.
Above 12 mBeam detector or ASDPoint detectors are not suitable. Use optical beam or aspirating smoke detection (ASD/VESDA).
Wall-Mounted Detectors
Smoke detectors mounted on walls: top of detector must be between 25mm and 600mm below the ceiling.
Heat detectors mounted on walls: top of detector must be between 25mm and 150mm below the ceiling.
Obstructions: Beams, joists, and partitions that project more than 10% of the ceiling height are treated as walls. Each bay between beams must be treated as a separate room for spacing purposes.
Access Control
Door Hardware Selection Guide
Electric locks · Magnetic locks · Strikes · Bolts · Fail-safe/secure · Current draw · Standards
Lock Type Comparison
Lock TypeFail ModeHolding ForceTypical CurrentBest For
Magnetic lock (magloc)Fail-safe (open)300–600 kg300–500 mA @ 12VFire escape routes, high-traffic doors.
Electric strikeFail-safe or fail-secureDepends on mechanical lock200–400 mA @ 12VTimber doors, low-medium security.
Electric boltFail-safe or fail-secure500–1000 kg300–500 mA @ 12VHigh-security, double doors.
Motorised lockFail-secure (typically)1000+ kg500 mA–1A @ 12VHigh-security, server rooms.
Electric rim lockFail-safe or fail-secureDepends on model200–400 mA @ 12VTimber doors, light commercial.
Fail-safe vs Fail-secure Decision
Fail-safe (fail-open): MANDATORY on all fire escape routes. Door must open freely without power. Magnetic locks are inherently fail-safe.
Fail-secure (fail-locked): Used where security is the priority (server rooms, cash offices). Must NOT be used on fire escape routes without a fire alarm override.
Always confirm fail mode with the fire risk assessor and building control before specifying.
Power Supply Sizing
Sum the current draw of all locks on each power supply. Add 20% headroom. Include the door controller current draw.
Example: 4 magnetic locks × 400mA = 1.6A + controller 200mA = 1.8A. Use a 3A PSU minimum.
Access control power supplies must provide 12V DC ±10% at the lock terminals. Voltage drop in cable must be accounted for.
Standards
BS EN 13637: Electrically controlled exit systems for use on escape routes.
BS EN 1125: Panic exit devices (push bar / push pad) — required on public escape routes.
BS EN 179: Emergency exit devices (lever handle) — for staff-only escape routes.
Fire Alarm
False Alarm Management
BS 5839-1 Clause 25 · Investigation · Alarm confirmation · FRS policy · Unwanted alarms
FRS policy: Many UK Fire and Rescue Services now operate a "confirmed alarm" policy — they will not attend unless the alarm is confirmed by a second activation, CCTV verification, or a keyholder. Excessive false alarms can result in the FRS withdrawing automatic attendance entirely.
Common Causes of False Alarms
CauseDetector Type AffectedRemedy
Steam / cooking fumesOptical smokeRelocate detector, fit heat detector in kitchen, use multi-sensor
Dust (construction)Optical smokeIsolate zone during works, clean detectors, use heat detector temporarily
Insects in detectorOptical smokeClean detector, fit insect-resistant detector
Aerosols / spraysOptical smokeRelocate detector, educate users, use multi-sensor
Detector end of lifeAll typesReplace detector (typically 10 years for smoke, 5 years for heat)
Loose connectionsAll typesCheck and tighten all connections on loop
Alarm Confirmation Methods (BS 5839-1 Clause 25)
Coincidence detection: Two detectors in the same zone must activate before alarm is raised. Reduces false alarms from single-detector faults.
Sequential confirmation: A second detector (in the same or adjacent zone) must activate within a set time period after the first.
Investigation mode: Panel delays the alarm output for a set period (typically 3 minutes) to allow a keyholder to investigate before the FRS is called.
CCTV verification: ARC operator views CCTV footage before calling FRS. Requires integration between fire alarm and CCTV systems.
Audio verification: ARC operator listens to audio from the premises before calling FRS.
Fire Alarm
Fire Alarm Integration with Other Systems
Access control · CCTV · BMS · Lifts · Suppression · Smoke control · Standards
Access Control Integration
Fail-safe requirement: All doors on designated escape routes must release (fail-safe open) on fire alarm activation. This is a legal requirement under the RRFSO 2005 and Building Regulations Approved Document B.
Integration method: Fire alarm panel relay output → access control panel input (or direct to door lock power supply). When the relay de-energises on alarm, power is removed from the lock, releasing the door.
Ensure the access control system is notified of the fire alarm condition so it can log the event and restore normal operation after reset.
CCTV Integration
Fire alarm can trigger CCTV to display the camera nearest to the alarm zone on the operator's screen (alarm pop-up).
Integration via: dry contact relay to NVR/VMS alarm input, or IP integration using manufacturer APIs (e.g. Genetec, Milestone).
BMS / BEMS Integration
Fire alarm panel provides: alarm relay output, fault relay output, and zone-by-zone status via BACnet, Modbus, or dry contacts.
BMS actions on fire alarm: AHU shutdown, smoke damper operation, pressurisation fan activation, smoke extract fan activation.
Lift Recall
On fire alarm, lifts must be recalled to the designated floor (usually ground) and taken out of normal service. Firefighting lifts remain available for fire brigade use.
Wiring: fire alarm relay → lift controller recall input. Must be tested during commissioning and annually.
Standard: BS EN 81-73 (Behaviour of lifts in the event of fire).
Gas Suppression Interface
Typically: 1 detector in zone = pre-alarm warning (abort opportunity). 2 detectors (coincidence) = discharge sequence initiated.
Pre-discharge: warning sounder activates (distinctive tone), abort button available (typically 30-second window).
Discharge: suppression panel releases agent. Fire alarm panel activates door releases, AHU shutdown, and ARC signalling.
Standard: BS EN 15004 (Gas extinguishing systems), BS ISO 14520.
Fire Alarm
Fire Risk Assessment — Engineer's Interface
What the FRA means for the engineer · System category · Responsible Person · Documentation
The Engineer's Role
The fire alarm engineer does not carry out the fire risk assessment — this is the responsibility of the Responsible Person (RP) or a competent fire risk assessor.
The engineer must read and understand the FRA before designing or modifying a fire alarm system. The FRA specifies the required system category (L1, L2, P1, etc.) and any specific detection requirements.
If no FRA exists, the engineer should advise the client that one is legally required under the RRFSO 2005 before proceeding.
Key FRA Outputs That Affect the System Design
FRA FindingImpact on System Design
System category (L1, L2, P1, etc.)Determines coverage area and detection density.
High-risk areas identifiedMay require additional detection or different detector types.
Sleeping risk (residential)Requires Grade D or Grade A system per BS 5839-6.
Phased evacuation requiredRequires voice alarm and staged sounder output.
Suppression system requiredRequires fire alarm integration with suppression panel.
Compartmentation breaches foundMust be remediated before system is commissioned.
Documentation Requirements
The fire alarm system design must be documented and provided to the RP. The O&M manual must include: as-installed drawings, commissioning certificate, cause and effect matrix, and maintenance schedule.
The log book must be maintained at the premises and updated after every visit (commissioning, service, fault attendance, false alarm).
For higher-risk buildings (HRBs) under the Building Safety Act 2022, all fire safety information must be included in the Golden Thread of information.
General
Handover Checklist & Documentation
Completion documentation · Client training · As-installed drawings · Certificates
Documentation to Provide at Handover
Commissioning certificate (signed by engineer)
As-installed drawings (zone plan, cable schedule, device schedule)
Panel programming printout or configuration backup
User manual (manufacturer's manual + site-specific user guide)
Log book (BS 5839-1 requires a log book for all fire alarm systems)
ARC monitoring confirmation (if applicable)
NSI/SSAIB certificate (if applicable)
Warranty documentation
Client Training — Minimum Requirements
How to silence and reset the alarm
How to arm and disarm the intruder alarm (if applicable)
How to change user codes
How to identify and respond to different alarm conditions
Weekly test procedure (fire alarm)
Who to call in an emergency and for maintenance
Intruder Alarm
Intruder Alarm Grades & Signalling Requirements
EN 50131 grades · PD 6662 · Signalling paths · Police response · URN allocation
EN 50131 Grades Summary
GradeRisk LevelTypical ApplicationKey Requirements
Grade 1LowDomestic, low-valueBasic tamper, simple signalling.
Grade 2Low–MediumMost commercial, domesticTamper, power monitoring, ARC signalling.
Grade 3Medium–HighHigh-value commercial, banksEnhanced tamper, dual-path signalling, 24hr ARC.
Grade 4HighCritical infrastructure, vaultsHighest tamper, encrypted signalling, continuous monitoring.
PD 6662 — UK Implementation
PD 6662:2017 is the UK guidance document for applying EN 50131. It defines specific requirements for UK installations including signalling path categories (SP2, SP4, SP6).
SP2: Single-path signalling (e.g. IP only). Suitable for Grade 2 non-police-response systems.
SP4: Dual-path signalling (e.g. IP + 4G). Required for Grade 2 police-response systems.
SP6: Dual-path with enhanced supervision. Required for Grade 3 police-response systems.
Police Response — URN Allocation
A Unique Reference Number (URN) is required for police to respond to an intruder alarm activation. Issued by the local police force.
Requirements for URN: system installed by NSI Gold or SSAIB-certified company, ARC monitoring to BS EN 50518, system meets Grade 2 minimum, keyholder available within 20 minutes.
Two false alarms in a rolling 12-month period will result in URN withdrawal (NPCC policy). Three false alarms in 3 months = automatic withdrawal.
URN can be reinstated after a 3-month false-alarm-free period and system inspection.
Signalling Protocols
ProtocolFormatNotes
Contact IDDTMF over PSTN/VoIPLegacy — still widely used. 4-digit account + event code.
SIA DC-09IP (TCP/UDP)Modern standard. Encrypted. Supports AES-128.
SIA DC-04PSTN/DTMFEnhanced Contact ID format.
Dualcom / EmizonIP + GSM dual-pathProprietary dual-path solutions widely used in UK.
General Reference
IP Network Setup for Security Systems
VLANs · PoE switches · Subnetting · Port forwarding · Cybersecurity
Network Segmentation — VLANs
Always isolate security systems on dedicated VLANs — do not share with corporate IT traffic. Recommended VLAN allocation: VLAN 10 = CCTV, VLAN 20 = Access Control, VLAN 30 = Fire/Intruder signalling.
Use managed PoE switches for IP cameras and access control readers. Unmanaged switches are not recommended for security installations.
Configure inter-VLAN routing only where required (e.g. VMS server on IT VLAN accessing camera VLAN). Use ACLs to restrict traffic.
IP Addressing
SystemRecommended SubnetNotes
CCTV cameras192.168.10.0/24Up to 254 cameras. Use .100–.254 for cameras, .1–.10 for infrastructure.
NVR/VMS server192.168.10.5 (static)Always assign static IPs to recording devices.
Access control192.168.20.0/24Controllers and servers on static IPs.
Fire/intruder signalling192.168.30.0/24Panel communicators on static IPs.
PoE Power Budget
PoE (802.3af): max 15.4W per port. Suitable for standard IP cameras and access readers.
PoE+ (802.3at): max 30W per port. Required for PTZ cameras, IR cameras, and some access control terminals.
PoE++ (802.3bt): max 60W or 100W per port. Required for high-power PTZ cameras and multi-sensor cameras.
Total switch PoE budget must exceed the sum of all connected device power requirements. Allow 20% headroom.
Cybersecurity Checklist
1
Change all default passwords on cameras, NVRs, switches, and access control panels before commissioning.
2
Disable unused services and ports on all network devices (e.g. Telnet, HTTP — use HTTPS/SSH only).
3
Enable firmware auto-update or schedule regular firmware updates for all IP devices.
4
Do not expose NVR or access control server directly to the internet — use VPN for remote access.
5
Document all IP addresses, MAC addresses, and credentials in the O&M manual. Store securely.
Port Reference
ServiceDefault PortNotes
RTSP (camera stream)554Change default where possible.
HTTP (camera web UI)80Disable — use HTTPS (443) instead.
HTTPS (camera web UI)443Enable TLS certificate.
Hikvision SDK8000Required for Hik-Connect and iVMS-4200.
Dahua SDK37777Required for DMSS and SmartPSS.
Axis VAPIX80/443HTTP/HTTPS only.
General Reference
Power Supply & Battery Standby Calculation
Current draw · Standby duration · Alarm load · BS 5839-1 / EN 50131 requirements
Standby Duration Requirements
SystemStandardStandby RequirementAlarm Duration
Fire alarm — L/P gradeBS 5839-124 hours standby30 minutes full alarm
Fire alarm — M gradeBS 5839-124 hours standby30 minutes full alarm
Intruder — Grade 2EN 5013112 hours standby4 minutes alarm
Intruder — Grade 3EN 5013112 hours standby4 minutes alarm
Access controlManufacturer / designTypically 4–8 hoursN/A
Battery Capacity Formula (BS 5839-1)
Required Ah = (Standby current × Standby hours) + (Alarm current × Alarm hours)
Add 25% ageing allowance: Battery Ah = Required Ah × 1.25
Worked Example — Fire Alarm
Standby current: 200mA (0.2A). Alarm current: 2A (all sounders). Required: 24 hrs standby + 0.5 hrs alarm.
Required Ah = (0.2 × 24) + (2 × 0.5) = 4.8 + 1.0 = 5.8 Ah
With 25% ageing: 5.8 × 1.25 = 7.25 Ah minimum battery capacity. Use 7.2 Ah or 12 Ah battery.
General
Systematic Fault Finding
Methodical approach to diagnosing faults on fire and intruder systems
General Approach
01
Read the panel display carefully. Note the exact fault description, zone number, and device address (if addressable).
02
Check the event log. When did the fault first appear? Was it after a power cut, maintenance visit, or change in weather?
03
Isolate the fault to a specific zone or device. Use the panel's zone test or fault isolation features.
04
Physically inspect the affected device. Check for: loose connections, corrosion, physical damage, insect ingress, condensation.
05
Test the cable. Use a multimeter to measure resistance and check for open circuits or short circuits.
Common Fault Patterns
FaultLikely CauseTest
Open circuit / line faultCable cut, loose connection, failed deviceMeasure resistance from panel. Infinite = open circuit. Disconnect devices one by one to isolate.
Short circuit / tamperCable damage, water ingress, device tamperedMeasure resistance. Near zero = short. Check cable route for damage. Check device for tamper.
Device fault (addressable)Failed detector, dirty detector, wiring fault at baseSwap detector head with known-good unit. Check base connections.
Intermittent faultLoose connection, thermal expansion, vibrationCheck all connections in the affected zone. Wiggle cables while monitoring panel.
Low batteryBattery end of life, high current draw, charger faultMeasure battery voltage under load. Check charger output voltage (typically 13.8V for 12V SLA).
Mains failBlown fuse, tripped MCB, power cutCheck consumer unit. Check fuse in panel. Check mains input voltage.
General Reference
Voltage Drop Calculation
Sounder circuits · Cable CSA selection · Maximum permitted drop · Worked examples
Formula
Voltage Drop (V) = Current (A) × Cable Resistance (Ω)
Cable Resistance (Ω) = (Resistivity × 2 × Length) ÷ CSA
Resistivity of copper = 0.0172 Ω·mm²/m
Maximum Permitted Voltage Drop
SystemMax Voltage DropBasis
Fire alarm sounder circuitTypically 10% of supply voltageBS 5839-1 / manufacturer spec
Intruder alarm bell circuitTypically 10% of supply voltageEN 50131 / manufacturer spec
Access control lock circuitTypically 5–10% (check lock spec)Manufacturer specification
Mains wiring (BS 7671)3% lighting, 5% powerBS 7671 Table 4Ab
Worked Example — Fire Alarm Sounder Circuit
Supply voltage: 24V DC. Max permitted drop: 10% = 2.4V. Total sounder current: 500mA (0.5A). Cable run: 80m one way (160m total). Cable CSA: 1.5mm².
Cable resistance = (0.0172 × 160) ÷ 1.5 = 1.835 Ω. Voltage drop = 0.5A × 1.835Ω = 0.92V (3.8%). Pass.
If using 0.5mm² cable: resistance = (0.0172 × 160) ÷ 0.5 = 5.504 Ω. Voltage drop = 0.5A × 5.504Ω = 2.75V (11.5%). Fail — upgrade to 1.0mm² or 1.5mm².
Quick Reference — Cable Resistance (Ω/km, both conductors)
CSAResistance (Ω/km, 2 conductors)
0.5mm²72.0 Ω/km
1.0mm²36.2 Ω/km
1.5mm²24.2 Ω/km
2.5mm²14.8 Ω/km
Fire Alarm
Walk Test Procedure — Fire Alarm
BS 5839-1 · Verify all detectors and call points · Do not trigger ARC
Before starting: Notify the ARC that you are carrying out a walk test. Agree a test period. Failure to notify may result in a false alarm attendance by the Fire and Rescue Service.
01
Put the panel into Walk Test mode (or Commissioning mode). This allows devices to be tested without triggering the full alarm output.
On most panels: Menu → Test → Walk Test. Refer to panel manual for exact procedure.
02
Activate each detector in turn using the appropriate test method:
• Optical smoke: use aerosol smoke test spray (Firecheck or equivalent)
• Heat detector: use a heat gun or hair dryer (do not use open flame)
• Multi-sensor: use smoke test spray (activates both optical and heat elements)
• Beam detector: use test filter or reflector alignment procedure
• CO detector: use CO test gas
03
Activate each manual call point using the test key. Do not break the glass element during testing.
04
Verify that each device activation is correctly identified on the panel display (correct zone and device address/label).
05
Verify that all sounders and VADs activate correctly when a zone is in alarm.
06
Verify all cause and effect outputs (door releases, AHU shutdown, lift recall, etc.).
07
Reset the panel after each test. Confirm the panel returns to normal status.
08
Record all test results on the commissioning certificate. Note any devices that failed to respond.
09
Notify the ARC that the walk test is complete.
Intruder Alarm
Walk Test Procedure — Intruder Alarm
Verify all zones · PIR coverage · Door contacts · Shock sensors
Before starting: Notify the ARC that you are carrying out a walk test. Put the panel into Engineer/Walk Test mode to prevent alarm signals being sent to the ARC.
01
Enter engineer access on the panel. Navigate to Walk Test or Zone Test mode.
02
Walk through each PIR detection zone. Walk slowly across the full detection pattern — near, mid, and far range. Verify the PIR triggers on the panel display.
03
Test each door contact by opening and closing the door/window. Verify the zone triggers and resets correctly.
04
Test each shock/vibration sensor by tapping the protected surface firmly. Verify the zone triggers.
05
Test each passive infrared curtain detector by walking through the detection beam.
06
Test each PA (personal attack) button by pressing it. Verify the panel registers the activation.
07
Verify entry/exit delays are correct. Arm the system and walk through the entry zone — confirm the entry delay starts and the keypad is reachable within the delay period.
08
Test the bell/sounder output by triggering an alarm (with ARC notified). Verify the external sounder and strobe activate.
09
Record all test results. Note any zones that failed to respond or showed incorrect behaviour.
General Reference
Wiring Standards & Cable Selection Reference
Cable types by system · Segregation rules · Screening · Containment · BS 7671
Cable Selection by System
SystemRecommended CableStandardNotes
Fire alarm — generalFP200 Gold 1.5mm² 2-coreBS 7629-1Enhanced fire performance. Red sheath.
Fire alarm — high riskMICC (Pyrotenax)BS EN 60702120 min fire resistance. Use in plant rooms, high-rise.
Intruder alarm6-core LSZH screenedBS 7211Screen to earth at panel end only.
Access controlCat5e/Cat6 (IP) or 4-core screened (Wiegand)BS 7671Max Wiegand cable run: 150m. Use Cat5e for longer runs with RS-485.
CCTV — IPCat5e/Cat6BS 7671Max PoE run: 100m. Use PoE extenders for longer runs.
CCTV — analogueRG59 or RG6 coaxBS 7671RG59 for runs up to 300m. RG6 for longer runs.
Segregation Rules
Fire alarm cables must be segregated from mains wiring. Minimum 50mm separation or use a metallic barrier (BS 5839-1 Clause 26).
Intruder alarm cables must be segregated from mains wiring by minimum 50mm or metallic barrier.
Do not run fire alarm cables and intruder alarm cables in the same containment.
Screened cables: connect screen to earth at one end only (panel end) to avoid earth loops.
Containment Types
ContainmentApplicationNotes
Steel conduitHigh-security, exposed areasProvides mechanical and EMI protection. Earth the conduit.
PVC conduitConcealed, domestic/light commercialNo EMI protection. Not suitable for fire alarm in high-risk areas.
Steel trunkingMultiple cables, plant roomsUse separate compartments for different systems.
Cable trayRoof voids, plant roomsOpen tray — no mechanical protection. Use armoured cable if exposed.
Fire Alarm
Zone Design — Fire Alarm (BS 5839-1)
Zone size limits · Multi-floor zones · Stairwells · Cause and effect · Zone plan
Zone Size Rules (BS 5839-1 Clause 12)
RuleLimitNotes
Maximum floor area per zone2,000 m²Applies to a single floor. Larger floors must be divided into multiple zones.
Maximum search distance60 mThe distance a person must walk to identify the fire location within a zone must not exceed 60m.
Multi-floor zonesNot recommendedZones should not cover more than one floor. Exception: small buildings where the total area is less than 300m².
Stairwells / lift shaftsSeparate zoneStairwells and lift shafts should each be a separate zone to allow rapid identification of fire location.
Cause and Effect Design
Simultaneous evacuation: Any zone activation triggers all sounders throughout the building. Simplest design, suitable for small buildings.
Phased evacuation: Alarm in one zone triggers evacuation of that zone and adjacent zones first. Remaining zones are alerted to stand by. Used in large buildings, hospitals, and high-rise.
Cause and effect matrix: Defines exactly which outputs activate in response to which inputs. Must be documented and agreed with the client and fire strategy consultant.
Ancillary outputs: Door releases (hold-open devices), AHU shutdown, lift recall, suppression system interface, and smoke control systems must all be included in the cause and effect matrix.
Zone Plan Requirements
A zone plan (floor plan showing all zones, detector positions, and call point positions) must be provided at the panel and at all repeater panels.
Zone plan must be kept up to date. Any changes to the building or system must be reflected in the zone plan.
Intruder Alarm
Zone Types — Intruder Alarm
Entry/exit · Instant · 24-hour · Final exit · PA · Tamper · Programming guidance
Zone TypeBehaviourTypical Use
Entry/ExitTriggers entry delay when system is armed. User must disarm within the entry delay period. Also triggers exit delay when arming.Front door, main entrance
Instant (Perimeter)Triggers alarm immediately when activated while system is armed. No delay.Windows, secondary doors, perimeter
Interior (Follower)Only active after the entry delay has expired. Allows user to walk through interior to reach keypad without triggering alarm.Internal PIRs on entry route
24-HourAlways active regardless of arm/disarm state. Triggers alarm at any time.Panic buttons, hold-up devices, fire door contacts
Final ExitTriggers exit delay. System arms when zone is secured. No entry delay — alarm is instant if re-entered while armed.Final exit door (no re-entry expected)
PA (Personal Attack)24-hour silent or audible alarm. Sends PA signal to ARC.Panic buttons, duress codes
Tamper24-hour. Triggers tamper alarm if device housing is opened.All devices — built into tamper circuit
KeyswitchArms or disarms the system when activated. Can be used as an alternative to keypad.External arm/disarm, shutter control
Entry and Exit Delay Guidelines
Entry delay: Minimum time for user to reach keypad and disarm. Typically 30–45 seconds. Must not exceed 45 seconds for Grade 2 (EN 50131).
Exit delay: Time for user to leave premises after arming. Typically 30–60 seconds. Must not exceed 45 seconds for Grade 2.
Alarm confirmation time: For confirmed alarm systems, the panel waits for a second activation before signalling the ARC. Typically 30 seconds.